1, Start and distribute
The entry point positioning dredger is self-sailing or towed to the position of the starting point of the groove, and the cutter suction dredger is positioned at the entry point positioning method. If the dredger is positioned downstream, when the dredger approaches the starting point of the grooving, it should first drop the leg anchor, then relax the Chao anchor cable to make the boat move forward downstream. When it reaches the starting point of the grooving, it should tighten the anchor cable, and then lower the bucket bridge to fix the hull. Such as countercurrent positioning, when the dredger arrived at the starting point of the groove, the first down the bucket bridge fixed position. After anchoring is completed, the ship position is recalibrated.
Throw the main anchor is also known as anchor collapse, according to the length of the groove and water conditions, as far as possible a thrown foot, reduces the number of anchor move.
In order to increase the climbing power of the main anchor, a section of the anchor chain, usually 2 to 5 sections (25m each, depending on the mud), can be attached to the anchor head.
The main anchor is generally thrown on the middle line of the trench, with a throw length of 600~1000m. The supporting cable barge is stopped at about 80~100m in front of the dredger to prevent the main anchor cable from sinking into the mud and affecting the transverse movement of the dredger. If the thickness of the mud layer is uneven in the grooving section, the main anchor cable should be slightly tilted to the side of the thick mud layer, so as to reduce the force on the anchor cable in front of the thick mud layer and facilitate the full excavation of the edge line.

(2) The distance to which the anchor is thrown is determined by the hardness and velocity of the soil in the dredging area. But because the leg anchor cable (chain) with the dredger gradually forward and elongated, so generally throw 150~200m can be. But in downstream construction, rapid water, hard soil, or too thin soft circumstances, the anchor should be cast farther. Anchor A is the same as the main anchor and can be thrown into the side of the trench where the line is tilted towards the thick mud layer.
(3) The side throwing the wrong side anchor is generally thrown 90~ 150m beyond the edge line of the groove. According to the water conditions, if the soil holds well, there is no large transverse wind, and the water is restricted, it can be shortened appropriately. The soil is hard, the force is large when moving horizontally, and it is easy to pull wrong, it can be lengthened appropriately. The anchor cable should be slightly forward when it is thrown laterally so that the front Angle with the midline of the groove should be maintained about 70~80.
Hot Tags: gold mining chain bucket dredger, China, suppliers, manufacturers, factory, price, for sale