An Example of Technical plan

 

Provided field data: the initial mud layer depth is 15 meters,the dredging depth is about 10-15 meters,and the average width of the lake is 10 meters.

So,considering small capacity ships,the total width is limited to about 5 meters (to be verified). The ship has no self-propelled capability and is towed by cables or yacht-like equipment.

 

Recommended ship structure

ship structure

 

The above structure is a reference structure. The cutter suction equipment is lowered vertically to the bottom of the river to pump mud and sand,and the mud discharge port is discharged from the stern end of the ship and connected to the mud discharge pipe.

working platformdredging

 

Parameter List

item

parameter

Remark

Planned daily dredging volume

1200m³/day

work for12 hours per day

Total dredging volume

900000m³

 

Engineering cycle

2.5 years finish

 

Main suction sand pump

parameters

Water:400m3/h,Head 50 meters,

speed 900rpm

 

Main suction sand pump

motor power

160kW

 

auxiliary reamer

22KWx2=44KW

 

main pump control

Frequency Control

 

Reamer Control

Frequency Control

 

Total capacity of power

transformer

400KVA,460V,60Hz

 

Drainpipe diameter

DN150

 

Material of mud pipe

PE+floating body

 

row spacing

2-3kilo

 

Control cabin

Integrated operation console,

transformer,frequency conversion

cabinet

 

 

ship structuretrodat